Acceleration Model for Completion of Infrastructure Projects Using the Foreign Loan Funding Scheme (Case Study: Dam X)

Total Views / Downloads: 99 

Cite ➜

Sutikno, D.S., 2021. Acceleration Model for Completion of Infrastructure Projects Using the Foreign Loan Funding Scheme (Case Study: Dam X). United International Journal for Research & Technology (UIJRT), 2(8), pp.168-173.

Abstract

In the process of working on the project, undesirable things can occur such as delays in project work that occur due to various factors such as unfavorable weather conditions, design changes and planning errors. There is also no exception in the implementation of projects with foreign loans, there are problems related to budget disbursement which can result in project delays. This study uses a questionnaire method to owners, supervisory consultants, and experienced contractors in dam construction to obtain a model for accelerating the completion of this project. The results of this study found that the 2 most dominant factors were in the main dam work category, namely extreme weather conditions and land availability in the dam construction area. The acceleration strategy used is the crashing method and the result is that the project completion is 93 days faster than the original implementation schedule. However, the consequence of this method is an increase in construction costs of 3,292,201,639.21 IDR.

Keywords: Foreign Loan, Dam, Acceleration, Infrastructure Project.

References

  1. Pambudi, S.W. (2014). “Identify factors that affect the performance of project implementation time with foreign loan funds at the pre-construction stage (case study: IDB Loan No. IND-01XX)”. Jakarta: Universitas of Indonesia.
  2. Sunaitan Al Mutairi (2017). “Analysis of Delays during Initial Phase of Construction Projects and Mitigation Measures”
  3. Ghada Taha, Mohamed Badawy, Omar El-Nawawy (2016). “A Model for Evaluation of Delays in Construction Projects”.
  4. Jyh-Bin yang and Pei-Rei Wei (2010). “Causes of Delay in the Planning and Design Phases for Construction Projects”.
  5. Adi, Nugroho. (2014). “Factors that Contribute to Construction Project Delay at PT. Newmont Nusa Tenggara.
  6. Taufiqur Rahman. 2013. “Project Management (Crashing Project)”. West Jakarta: Faculty of Engineering, Esa Unggul University.
  7. Anonim (2000). “Study of The Effectiveness of the Use of Foreign Loan Funds”. Directorate General of Budget, Ministry of Finance, Jakarta.
  8. Ervianto, Wulfram I. (2005). “Construction Project Management (Revised Edition)”. Yogyakarta: CV. Andi Offset.